The GW99.99K-ETR-G10 is rated 99.99 kW AC with 200 kW maximum PV input on 10 MPPTs. Backup requires an STS Box or STS Cabinet.

AC limit
99.99 kVA maximum
Rated AC output
99.99 kW
Max PV input
200 kWp
MPPT
10
Battery voltage
700 – 1000 V

Model comparison

Grid-Threshold Selection Note

For German EEG remuneration and direct marketing, compare the installed PV capacity with the 100 kW threshold in § 21 EEG. Under § 13a EnWG, redispatch covers plants rated at least 100 kW and units the grid operator can control remotely.

Datasheet ratingCurrent modelGW99.99K-ETR-G10GW100K-ETR-G10
Maximum apparent power to grid99.99 kVA110 kVA
Maximum grid current at 400 V144.4 A158.8 A
Maximum charge and discharge power99.99 kW110 kW
Rated AC active power99.99 kW100 kW
Compare GW100K-ETR-G10 (110 kVA maximum) →

GoodWe GW99.99K-ETR-G10 (99.99 kW three-phase hybrid inverter)

  • 99.99 kW continuous output (99.99 kW max) on 3L/N/PE.

  • 200 kW PV on 10 MPPTs, 2 strings per tracker, 42 A / 55 A.

  • One 700–1000 V LFP port at 142.8 A / 99.99 kW; pairing with GW261.2-BAT-LCD-G10, Voc > 813 V.

  • Backup path needs an STS Box or STS Cabinet; switchover <10 ms on one unit.

Takes 99.99 kW on a 700 to 1000 V battery bus

The battery port operates from 700 to 1000 V with a 750 V nominal rating and 700 V start-up. Continuous charge and discharge current reaches 142.8 A. The Battery Compatibility Overview names GW261.2-BAT-LCD-G10 for ETR 80–125 kW; PV string Voc must sit above 813 V with that cabinet.

Fits 200 kW across 10 MPPT channels

10 MPPT trackers handle 42 A each with 2 strings per tracker. Operating voltage spans 160 to 1000 V with a 1100 V maximum input rating. Between 1000 V and 1100 V the inverter stands by and returns to work at 1000 V.

Holds 99.99 kVA backup with an external STS

Backup power provides 99.99 kVA nominal and 99.99 kVA max with an STS Box or STS Cabinet on the path. Peak without grid: 120% for 60 s; 150% for 10 s. Switchover time is under 10 ms on one unit.

IP66 wall unit, 96 kg

The wall-mounted unit measures 995 × 758 × 358 mm and weighs 96 kg. Intelligent air cooling, 60 dB noise emission and −35 to +60 °C operation. Remote shutdown is integrated.

Technical data

AC Output (On-Grid)
Rated / max. power
99.99 kW rated / 99.99 kW max (GW99.99K-ETR-G10)
Rated / max. apparent power
99.99 kVA / 99.99 kVA
Rated / max. current at 400 V
144.4 A / 144.4 A
Nominal voltage
220/380, 230/400, 240/415 V, 3L/N/PE, 50/60 Hz
Power factor / THDi
~1, adjustable 0.8 leading – 0.8 lagging / THDi <3%
PV Input
Max. PV input power
200 kW maximum PV input (GW99.99K-ETR-G10)
Max. input voltage
1100 V (standby above 1000 V)
MPPT operating voltage range
160–1000 V; start-up 200 V; nominal 620 V
MPPTs / strings
10 MPPTs, 2 strings per MPPT
Max. MPPT current / short-circuit current
42 A / 55 A per MPPT
Battery Interface
Battery type / voltage window
LFP; 700–1000 V, nominal 750 V, start-up 700 V, one battery connection port
Max. charge / discharge power
99.99 kW
Max. continuous charge / discharge current
142.8 A
Compatible battery system
ETR 80–125 kW: GW261.2-BAT-LCD-G10; PV string Voc must exceed 813 V with that cabinet.
Backup (with STS)
Nominal / max. backup apparent power
99.99 kVA / 99.99 kVA; STS Box or STS Cabinet required
Peak output power without grid
120% for 60 s; 150% for 10 s
On/off-grid switching time
<10 ms (one unit)
Efficiency & General
Max. / European efficiency
98.1% / 97.7%
Max. battery-to-AC efficiency
98.2%
Enclosure / environment
IP66, -35 to +60 °C, 0–100% RH, max. 4,000 m, intelligent air cooling, noise 60 dB
Dimensions / weight / mounting
995 × 758 × 358 mm / 96 kg / wall-mounted
Communication
RS485, Wi-Fi, LAN, Bluetooth, 4G; Modbus TCP (SunSpec compatible); CAN to BMS; LED + optional LCD + app
Inverter package
Includes GM330 meter × 1, smart dongle × 1, 10 m meter cable, 5 m parallel cable, PV and battery connectors

Documents

Product questions

Is an external STS needed for the ETR backup path?

Yes. The inverter can only use the BACK-UP function when paired with STS. The STS Box or STS Cabinet is needed.

Can PV strings operate in the 1000–1100 V band?

For the GW99.99K-ETR-G10, when the input voltage ranges from 1000 V to 1100 V, the inverter enters standby mode. Normal operation resumes when the voltage returns to 1000 V.

Compatibility records

Compatible modelCategoryRatingStatus & required accessory
GoodWe GW261.2-BAT-LCD-G10Item number DLK-GOODWE-GW2612BATLCDG10Battery Systems261.2 kWhReleased [1]
  1. GoodWe's Battery Compatibility Overview (p. 6) lists GW261.2-BAT-LCD-G10 in its ETR 80–125 kW column, which covers the GW80K/99.99K/100K/110K/124.99K-ETR-G10 models. The ETR 80–125 kW datasheet (EMEA, p. 2) prints that series; the user manual's single-unit and parallel tables list the battery for the series.
View full inverter & battery compatibility matrix

Compare models in this series

ModelRated AC outputMax PV inputPhasesMPPTBattery voltageMatched batteriesGrid standardAC limitProtection
GW80K-ETR-G1080 kW160 kWp38700 – 1000 V1EN 50549——
GW99.99K-ETR-G1099.99 kW200 kWp310700 – 1000 V1—99.99 kVA maximum—
GW100K-ETR-G10100 kW200 kWp310700 – 1000 V1—110 kVA maximum—
GW110K-ETR-G10110 kW220 kWp310700 – 1000 V1EN 50549——
GW124.99K-ETR-G10124.99 kW250 kWp310700 – 1000 V1—124.99 kVA maximumIP66
GW125K-ETR-G10125 kW250 kWp310700 – 1000 V2—137.5 kVA maximum—

Planning & Commissioning Guides