The GW124.99K-ETR-G10 is rated 124.99 kW AC with 250 kW maximum PV input on 10 MPPTs. Backup requires an STS Box or STS Cabinet.

AC limit
124.99 kVA maximum
Rated AC output
124.99 kW
Max PV input
250 kWp
MPPT
10
Battery voltage
700 – 1000 V

Model comparison

Grid-Threshold Selection Note

For a German medium-voltage connection, assess the 135 kW boundary using active power, including existing generation at the connection. The certification route under VDE-AR-N 4110 and NELEV also depends on total installed capacity and agreed export power.

Datasheet ratingCurrent modelGW124.99K-ETR-G10GW125K-ETR-G10
Maximum apparent power to grid124.99 kVA137.5 kVA
Maximum grid current at 400 V180.5 A198.5 A
Maximum charge and discharge power124.99 kW137.5 kW
Maximum on-grid active power124.99 kW137.5 kW
Compare GW125K-ETR-G10 (137.5 kVA maximum) →

GoodWe GW124.99K-ETR-G10 (124.99 kW three-phase hybrid inverter)

  • 124.99 kW continuous output (124.99 kW max) on 3L/N/PE.

  • 250 kW PV on 10 MPPTs, 2 strings per tracker, 42 A / 55 A.

  • One 700–1000 V LFP port at 178.5 A / 124.99 kW; pairing with GW261.2-BAT-LCD-G10, Voc > 813 V.

  • Backup path needs an STS Box or STS Cabinet; switchover <10 ms on one unit.

Takes 124.99 kW on a 700 to 1000 V battery bus

The battery port operates from 700 to 1000 V with a 750 V nominal rating and 700 V start-up. Continuous charge and discharge current reaches 178.5 A. The Battery Compatibility Overview names GW261.2-BAT-LCD-G10 for ETR 80–125 kW; PV string Voc must sit above 813 V with that cabinet.

Fits 250 kW across 10 MPPT channels

10 MPPT trackers handle 42 A each with 2 strings per tracker. Operating voltage spans 160 to 1000 V with a 1100 V maximum input rating. Between 1000 V and 1100 V the inverter stands by and returns to work at 1000 V.

Holds 124.99 kVA backup with an external STS

With an STS Box or STS Cabinet, one unit supplies 124.99 kVA of backup apparent power. Off-grid peak ratings are 120% for 60 s and 150% for 10 s. Transfer takes less than 10 ms on a single unit.

IP66 wall unit, 98 kg

The wall-mounted unit measures 995 × 758 × 358 mm and weighs 98 kg. Intelligent air cooling, 60 dB noise emission and −35 to +60 °C operation. Remote shutdown is integrated.

Technical data

AC Output (On-Grid)
Rated / max. power
124.99 kW rated / 124.99 kW max (GW124.99K-ETR-G10)
Rated / max. apparent power
124.99 kVA / 124.99 kVA
Rated / max. current at 400 V
180.5 A / 180.5 A
Nominal voltage
220/380, 230/400, 240/415 V, 3L/N/PE, 50/60 Hz
Power factor / THDi
~1, adjustable 0.8 leading – 0.8 lagging / THDi <3%
Maximum grid current at 380 V
190.0 A
Maximum grid current at 415 V
174.0 A
PV Input
Max. PV input power
250 kW maximum PV input (GW124.99K-ETR-G10)
Max. input voltage
1100 V (standby above 1000 V)
MPPT operating voltage range
160–1000 V; start-up 200 V; nominal 620 V
MPPTs / strings
10 MPPTs, 2 strings per MPPT
Max. MPPT current / short-circuit current
42 A / 55 A per MPPT
Battery Interface
Battery type / voltage window
LFP; 700–1000 V, nominal 750 V, start-up 700 V, one battery connection port
Max. charge / discharge power
124.99 kW
Max. continuous charge / discharge current
178.5 A
Compatible battery system
ETR 80–125 kW: GW261.2-BAT-LCD-G10; PV string Voc must exceed 813 V with that cabinet.
Backup (with STS)
Nominal / max. backup apparent power
124.99 kVA / 124.99 kVA; STS Box or STS Cabinet required
Peak output power without grid
120% for 60 s, 150% for 10 s
On/off-grid switching time
<10 ms (one unit)
Efficiency & General
Max. / European efficiency
98.1% / 97.7%
Max. battery-to-AC efficiency
98.2%
Enclosure / environment
IP66, -35 to +60 °C, 0–100% RH, max. 4,000 m, intelligent air cooling, noise 60 dB
Dimensions / weight / mounting
995 × 758 × 358 mm / 98 kg / wall-mounted
Communication
RS485, Wi-Fi, LAN, Bluetooth, 4G; Modbus TCP (SunSpec compatible); CAN to BMS; LED + optional LCD + app
Inverter package
Includes GM330 meter × 1, smart dongle × 1, 10 m meter cable, 5 m parallel cable, PV and battery connectors
MPPT efficiency
99.9%
Grid documents on this page
VDE-AR-N 4105, EN 50549-1, EN 50549-2, IEC 61727 / IEC 62116, EU Declaration of Conformity

Project fit

Where this model fits.

Scenarios that show which projects the GoodWe GW124.99K-ETR-G10 (124.99 kW three-phase hybrid inverter) belongs in, and the limits behind our engineers' recommendation.

01
Project scenario

Working within an existing grid connection

A business adding battery storage to an existing connection needs three separate figures for the grid application: active power, apparent power and line current. On the GW124.99K-ETR-G10 the rated and maximum grid outputs coincide. They are 124.99 kW of active power and 124.99 kVA of apparent power.

At 400 V the maximum line current is 180.5 A. The GW125K-ETR-G10 has the same rated current, but its maximum reaches 198.5 A. That higher figure changes the design of the AC path. Use the column for the selected model when specifying switchgear or comparing the available capacity of an existing connection.

Limits for the configuration
  • Record the maximum active and apparent power of each unit on the single-line diagram.
  • Include existing equipment when checking the agreed export capacity.
02
Project scenario

Dividing a commercial rooftop between ten trackers

Roof areas with different orientations can use separate trackers. The inverter accepts up to 250 kW of PV input across ten MPPTs. Each tracker has two string inputs, giving twenty inputs in total. The two strings on one tracker share its operating point and its current limit.

Add the operating currents of the parallel strings before checking the 42 A limit per tracker. Check the combined short-circuit current against 55 A as a separate step. Voltage needs a temperature check too. The tracking window is 160 to 1000 V, with start-up at 200 V. The 1100 V maximum is an input limit. Above 1000 V the inverter enters standby and resumes normal operation when the voltage returns to 1000 V.

Limits for the configuration
  • Calculate the operating and short-circuit currents for the actual strings on each tracker.
  • Use the module temperature coefficients when checking the string voltage range.
03
Project scenario

Sizing battery power for a measured demand peak

A demand peak has both a magnitude and a duration. The inverter can charge or discharge at up to 124.99 kW. How long the battery can sustain the required output depends on available energy, state of charge and the operating limits of the selected cabinet. Plotting the measured peak against time gives the starting point for choosing the usable capacity.

GoodWe lists GW261.2-BAT-LCD-G10 for this ETR range in its Battery Compatibility Overview V029.1, page 6. The inverter has one battery port, with a nominal voltage of 750 V and a working range of 700 to 1000 V. Its continuous charge and discharge current limit is 178.5 A. A proposed operating point has to satisfy the voltage, current and power limits together.

Limits for the configuration
  • Read the required discharge power and duration from the site load trace.
  • Record the cabinet model and applicable firmware in the system design.
04
Project scenario

Backing up critical loads and adding parallel units

Where only selected loads must stay online during an outage, define that circuit separately from the normal grid supply. The ETR datasheet specifies an external STS Box or STS Cabinet for backup. With one inverter it gives a transfer time below 10 ms. Rated and maximum backup apparent power on this model are both 124.99 kVA.

Motor starts and refrigeration loads add a duration constraint. The off-grid peak ratings for this model are 120% for 60 seconds and 150% for ten seconds. Use the continuous rating for normal operation and compare the measured or specified starting demand with the appropriate time window. Allow mounting space for a 98 kg IP66 wall unit and the installation clearances specified for cooling and service.

Limits for the configuration
  • List the continuous demand and the starting demand of the critical circuits separately.
  • Include transfer equipment and the parallel controller as distinct components of the design.

Documents

Product questions

Is an external STS needed for the ETR backup path?

Yes. The manual states that the inverter can only use the BACK-UP function when paired with STS. The datasheet footnote also states that the STS Box or STS Cabinet is needed. The inverter-to-STS communication cable is included with the unit.

Can PV strings operate in the 1000–1100 V band?

No. For the GW124.99K-ETR-G10, when the input voltage ranges from 1000 V to 1100 V, the inverter enters standby mode. The voltage must return to 1000 V for the inverter to enter the normal operation state.

Compatibility records

Compatible modelCategoryRatingStatus & required accessory
GoodWe GW261.2-BAT-LCD-G10Item number DLK-GOODWE-GW2612BATLCDG10Battery Systems261.2 kWhReleased [1]
  1. GoodWe's Battery Compatibility Overview (p. 6) lists GW261.2-BAT-LCD-G10 in its ETR 80–125 kW column, which covers the GW80K/99.99K/100K/110K/124.99K-ETR-G10 models. The ETR 80–125 kW datasheet (EMEA, p. 2) prints that series; the user manual's single-unit and parallel tables list the battery for the series.
View full inverter & battery compatibility matrix

Compare models in this series

ModelRated AC outputMax PV inputPhasesMPPTBattery voltageMatched batteriesGrid standardAC limitProtection
GW80K-ETR-G1080 kW160 kWp38700 – 1000 V1EN 50549——
GW99.99K-ETR-G1099.99 kW200 kWp310700 – 1000 V1—99.99 kVA maximum—
GW100K-ETR-G10100 kW200 kWp310700 – 1000 V1—110 kVA maximum—
GW110K-ETR-G10110 kW220 kWp310700 – 1000 V1EN 50549——
GW124.99K-ETR-G10124.99 kW250 kWp310700 – 1000 V1—124.99 kVA maximumIP66
GW125K-ETR-G10125 kW250 kWp310700 – 1000 V2—137.5 kVA maximum—

Planning & Commissioning Guides